Skegness Gateway unveils £151m flood defence plan

Sue Bowser and Neil Sanderson of Croftmarsh.Sue Bowser and Neil Sanderson of Croftmarsh.
Sue Bowser and Neil Sanderson of Croftmarsh.
A £151 million Flood Risk Resilience Fund (FRRF) has been announced as part of a raftof measures that will help defend the development and wider Skegness area from the impacts of flooding.

The plans, revealed by the owners behind the landmark Skegness Gateway scheme, have been collaboratively developed with East Lindsey District Council and the Environment Agency and have been more than 12 months in planning.

This follows the approval of a Local Development Order (LDO) for the scheme in March, announced at an executive meeting of East

Lindsey District Council in Horncastle.

Hide Ad
Hide Ad
A 3D map of the proposed Skegness Gateway.A 3D map of the proposed Skegness Gateway.
A 3D map of the proposed Skegness Gateway.

Agreement was given on more than £300m in socio-economic benefits for the region, alongside new homes, jobs, a crematorium and supported living provision. A new TEC college was granted planning permission for the site in February 2023.

The unique FRRF scheme will operate via an ongoing management fee, associated with the 1,000 properties planned for the 336-acre site.

A specialist estate management company will be formed alongside this, which will manage the financial model and take an active role in flood risk strategy on site.

A proportion of the money received from the Gateway properties will allow funding agreements to be setup between East Lindsey District

Hide Ad
Hide Ad

Council (ELDC), the Environment Agency (EA) and other vested interest parties for ongoing defence management and flood risk reduction over the lifetime of the development.

Sue Bowser, of Croftmarsh, said: “The Gateway team take the issue of flooding very seriously. It’s one of the key reasons we have

generated this funding, which contributes positively to schemes that maintain and mitigate against the risks posed by flooding and water management.

“We’ve worked hard to come up with a solution that not only protects our development, but also our wider home of Skegness, closely

Hide Ad
Hide Ad

collaborating with the Environment Agency and East Lindsey District Council.

“Regenerating the area is hugely important to us as a fifth-generation family in the area, and we’re pleased to see the acceleration

of a scheme that will bring new homes, jobs and greater prosperity to our region.”

According to the latest Climate Change Risk Assessment, an estimated 1.8m people are living in areas of the UK at significant risk

of coastal, surface or river flooding.

Hide Ad
Hide Ad

In Skegness, the Gateway’s Flood Risk Assessment (FRA) identifies the coastline defending the project to be 13.8km, running from Burgh

Sluice to the main drain outfall at Ingoldmells. Estimates from the Environment Agency put defence management for the next 100-year period, from Saltfleet to the Gibraltar Point coastline, as ranging between £15m per kilometre to £40m per kilometre.

The contribution enabled by the FRRF scheme could cover 27.0% of the defence management at the highest rate and 71.9% at the lowest

rate, depending on the approach and measures taken to flood prevention efforts in the region.

Hide Ad
Hide Ad

Neil Sanderson, also of Croftmarsh, added: “We understand the flooding risks posed to coastal communities across the UK and want to

be active in the role we can play in mitigation efforts.

“What we have here is a solution that is bespoke for our town, allowing regenerative efforts to flourish whilst contributing positively

to flood defence strategies being undertaken by public sector organisations.”

As part of the Gateway’s flood prevention efforts, a series of flood education and evacuation programmes will also be undertaken by

Hide Ad
Hide Ad

the estate management team, extending to new homeowners as well as the wider population of Skegness.

Raised ground and flood compensation areas are all part of the Gateway’s proposals, aiding flood prevention onsite.

Councillor Steve Kirk, East Lindsey District Council portfolio holder for coastal economy, said: “I am delighted we have been able to

agree this significant investment and commitment to help protect this landmark development and the wider area from flooding for many years to come.

Hide Ad
Hide Ad

“The risk of flooding and the devastating impact it can have must always be taken extremely seriously, and working in partnership with

transformational projects like this we can help make real improvements and additions that will safeguard Skegness and its residents and businesses for generations to come.”  

Chris Baron, chair of Connected Coast commented: “It is great that this level of commitment is being made to support flood resilience as part of the Skegness Gateway. We have such a fantastic opportunity to invest and deliver transformational improvements for the area through all of our work, and doing this responsibly and respectfully of the environment

is crucial.”

To find out more about the Skegness Gateway project, visit

https://skegnessgateway.co.uk/

Comment Guidelines

National World encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Follow us
©National World Publishing Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice