£1.5m track investment to deliver more reliable journeys between Lincoln and Cleethorpes

Replacement buses will be needed for travellers using the rail service through Market Rasen on the weekend of October 17 and 18 while Network Rail renews a section of track.

The £1.5 million investment will renew nearly 1.2km of track near Snelland, to deliver smoother, more reliable journeys for passengers travelling between Lincoln and Cleethorpes.

Passengers are advised that the work means buses will replace trains between Cleethorpes and Lincoln/Barton-on-Humber on Saturday and Sunday October 17-18.

Snelland level crossing, on Station Road, will be closed to vehicles and pedestrians from 10pm on Friday October 16 until 5.30am on Monday October 19, according to Network Rail. A signed diversion route via the B1202, B1399 and A158 will be in place.

Snelland level crossing. Network Railplaceholder image
Snelland level crossing. Network Rail

The track renewal project will replace worn out track components, reducing the need for maintenance and the chance of a temporary speed restriction being needed in the future. Network Rail engineers will use nine engineering trains, road-rail vehicles and other specialist equipment to complete the work.

Eric Larocque, Network Rail’s East Midlands operations director, said: “We’re sorry for the disruption and thank passengers and local residents for their patience while we complete these important improvements.”