Work starts to install 57km of cable for £2bn wind farm

Work to install over 57km of underground cable from Anderby Creek to Bicker Fen as part of the £2bn Triton Knoll Offshore Wind Farm project begins today.

The work includes the upgade of a substation at Bicker Fen to deliver over 860MW of wind energy into the UK.

Work is beginning on the £2bn Triton Knoll Offshore Wind Farm project. ANL-181009-080310001placeholder image
Work is beginning on the £2bn Triton Knoll Offshore Wind Farm project. ANL-181009-080310001

That’s enough to power the equivalent of circa 800,000 UK homes, or more than all the homes in Lincolnshire and North East Lincolnshire combined.

A breaking ground ceremony is taking place at J Murphy & Sons (JMS) Compound, on Main Road (A16), Stickney, this afternoon.