'This scheme is critical': Major roadworks underway ahead of 2026 Skegness improvements

Preparatory works are set to begin on two key Skegness routes ahead of major improvements planned for 2026.

Lincolnshire County Council is carrying out these schemes to ensure safer, more efficient roads and improved traffic management for residents and visitors.

A £160,000 traffic signal upgrade on the A158 Gunby Road/Orby Lane is planned to bring the junction up to modern standardsplaceholder image
A £160,000 traffic signal upgrade on the A158 Gunby Road/Orby Lane is planned to bring the junction up to modern standards

On the A52 Croft Bank/Wainfleet Road, between Heath Road and Croft Marsh Lane, a £50,000 preparatory scheme will take place overnight on Wednesday, December 10, and Thursday, December 11.

Working hours will run from 7pm to 6.30am to minimise disruption. A full road closure will be in place, with a signed diversion using like-for-like roads to guide traffic around the area. Access for residents within the closure will be maintained, with on-site operatives available to assist.

Karen Cassar, assistant director for Highways at Lincolnshire County Council, said: “This scheme is critical to get the right preparations in place for next year’s wider surface dressing programme. When completed, it will improve skid resistance, road texture and waterproofing. We will also be re-lining the road and replacing road studs. We thank everyone affected for their patience while we carry out this work.”

Meanwhile, on the A158 Gunby Road/Orby Lane, a £160,000 traffic signal upgrade is planned to bring the junction up to modern standards. The existing signals have reached the end of their operational life, with spare parts becoming obsolete. The works, scheduled from Monday, January 5, to Friday, February 13, 2026, will replace all traffic signal equipment, loops, ducting, duct chambers, lids, and some kerbing. A new low-voltage controller and maintenance parking area will also be installed, improving safety and efficiency while reducing the carbon footprint.

Traffic management for the A158 works will include three-way temporary signals, a temporary 30mph speed limit, and a No Right Turn manoeuvre off the A158. Weekday working hours will be 7.30am to 5pm, with the potential for weekend work if required.

Karen Cassar added: “The new signal equipment will be more efficient and safer for road users, and the improvements will ensure that maintenance can be carried out safely in the future. We will do everything possible to complete these works quickly and thank everyone affected for their patience and understanding.”

Residents and road users are encouraged to check www.lincolnshire.gov.uk/roadworks for the latest updates on these and other local schemes.